AdvanceReceived
Due 08 Aug 2026
Expected
₹24,00,000.00
Received
₹24,00,000.00
Pending
₹0.00
Notes
Initial advance
Record Activity
BANK_TRANSFER
02 Sept 2026
₹24,00,000.00
Cedar Villa
Plan expected collections, record receipts and spot overdue payments immediately.
Overview
Project Amount
₹49,50,000.00
Received
₹24,00,000.00
Outstanding
₹25,50,000.00
Overdue
₹0.00
Payment Planning
How much of the current project amount has a payment schedule.
97% scheduled
Scheduled
₹48,00,000.00
Unscheduled
₹1,50,000.00
Payments Received
0 direct payments
Payments recorded without a payment schedule will appear here.
Payment Schedule
2 scheduled payments
Due 08 Aug 2026
Expected
₹24,00,000.00
Received
₹24,00,000.00
Pending
₹0.00
Notes
Initial advance
Record Activity
BANK_TRANSFER
02 Sept 2026
₹24,00,000.00
Due 12 Oct 2026
Expected
₹24,00,000.00
Received
₹0.00
Pending
₹24,00,000.00
Notes
Final handover